A and B together can complete work in 6 days.
A and B together can complete work in 6 days. A alone starts working and leaves it after working for 3 days completing only half of the work. In how many days it can be completed if the remaining job is undertaken by B?
Answer/Solution
3
Steps/Work
Explanation:
(A+B) one day work =1/6
now A does half of the work in 3 days so A can complete the whole work in 6 days
A’s one day work =1/6
B’s one day work=1/6 - 1/6= 1/6
B alone can complete the work in 6 days so half of the work in 3 days
Answer: Option A
(A+B) one day work =1/6
now A does half of the work in 3 days so A can complete the whole work in 6 days
A’s one day work =1/6
B’s one day work=1/6 - 1/6= 1/6
B alone can complete the work in 6 days so half of the work in 3 days
Answer: Option A