60 boys can complete a work in 40 days.how many men need to complete twice the work in 20 days
60 boys can complete a work in 40 days.how many men need to complete twice the work in 20 days
Answer/Solution
240
Steps/Work
one man can complete the work in 40*60=2400 days = one time work
to Complete the work twice it will be completed in
let M be the no. of worker assign for this therefore the eqn becomes
M*20=2*2400
M=240 workers
ANSWER:E
to Complete the work twice it will be completed in
let M be the no. of worker assign for this therefore the eqn becomes
M*20=2*2400
M=240 workers
ANSWER:E