A and B can do a piece of work in 7 days.
A and B can do a piece of work in 7 days. With the help of C they finish the work in 4 days. C alone can do that piece of work in?
Answer/Solution
9 1/3
Steps/Work
C = 1/4 – 1/7 = 3/28 => 28/3 = 9 1/3 days
Answer: B
Answer: B