A and B can finish a work in 12 days while A alone can do the same work in 20 days.
A and B can finish a work in 12 days while A alone can do the same work in 20 days. In how many days B alone will complete the work?
Answer/Solution
30 days
Steps/Work
B = 1/12 – 1/20 = 2/60 = 1/30=> 30 days
Answer: B