24 men working at 8 hours a day can finish a work in 10 days.
24 men working at 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is?
Answer/Solution
32
Steps/Work
Using Using the chain rule,
M1 x T1 = M2 x T2
Therefore, 24 x 8 x 10 = 10 x X x 6
X= 32
Hence, the number of men required to finish the work = 32.
ANSWER:B
M1 x T1 = M2 x T2
Therefore, 24 x 8 x 10 = 10 x X x 6
X= 32
Hence, the number of men required to finish the work = 32.
ANSWER:B