If 24 men take 15 days to to complete a job, in how many days can 18 men finish that work?

If 24 men take 15 days to to complete a job, in how many days can 18 men finish that work?

Quiz

Answer/Solution

20

Steps/Work

Ans. 20 days

Physics Calculator / Auto Solver

If men take days to to complete a job, in how many days can men finish that work?

Calculated Answer

20

Step by Step Solution

In order to solve problem, you must evaluate (n0 * n1) / n2.

n0 =24
n1 =15
n2 =18