A constructor estimates that 8 people can paint Mr khans house in 3 days.

A constructor estimates that 8 people can paint Mr khans house in 3 days. If he uses 4 people instead of 8,how long will they take to complete the job?

Quiz

Answer/Solution

6

Steps/Work

Explanation:
Use formula For a work Members × days = constant
8 × 3 = 4 × a
a = 6
so answer is 6 days
Answer: A